World Bank downgrades $150m Punjab education project over delays
The World Bank has lowered its implementation rating for the $150 million GRADES education project in Punjab from satisfactory to moderately satisfactory. It cited delayed technical assistance, missing baseline data and a slow start to classroom construction.

- Implementation progress cut from 'satisfactory' to 'moderately satisfactory'
- Delays in technical assistance, missing baseline data and no classroom construction yet
- Enrolment in public-private partnership schools reached its fourth-year target early
- Financing runs until June 2029
The World Bank has downgraded the implementation progress of a $150 million education project in Punjab, according to reports by Minute Mirror and Daily Times. In its latest public disclosure, the lender moved the rating from "satisfactory" to "moderately satisfactory".
The project is called Getting Results: Access and Delivery of Quality Education Services in Punjab, or GRADES. The bank gave three reasons for the lower rating: delays in securing technical assistance, baseline data that is still missing, and a slow start to classroom construction.
The bank did not change two other assessments. Progress towards the development objectives stays at moderately satisfactory, and the overall risk rating remains moderate.
The disclosure also reports gains. Enrolment in public-private partnership schools has risen significantly, and the fourth-year target was met ahead of schedule. In addition, 1,092 schools now offer early childhood care and education that meets the prescribed quality standards. The project also met its financial targets for the previous fiscal year and moved forward on several performance-based conditions.
Construction of additional classrooms has not yet begun, although preliminary preparations are complete. The government has revised its classroom construction strategy, and carrying it out would require formal restructuring of the project. Daily Times reported that the World Bank stressed this restructuring was essential.
The missing baseline data is expected to be dealt with during the restructuring, and officials are to mobilise the delayed technical support at the same stage, according to the reports.
The World Bank's executive directors approved the project in June 2024, and financing is scheduled to run until June 2029. It aims to raise the enrolment of girls and boys in pre-primary and primary education and to improve primary reading skills in Punjab. It is meant to make up for learning losses from Covid-19, strengthen school management, improve teaching and widen access.
The project is expected to reach about five million children, 7,000 headteachers, 165,000 teachers and over 3,000 teacher mentors in government schools and institutions run by the Punjab Education Foundation. More than seven million children in Punjab were out of school as of June 2024.
Why it matters for Pakistan
The project is meant to support school education across Punjab, and its classroom construction has not yet started. About five million children and 165,000 teachers are expected to benefit once it is delivered. More than seven million children in the province were out of school as of June 2024, so enrolment and early reading are the project's central aims. The restructuring the World Bank describes as essential will decide when the planned classrooms and reforms can begin.