Margalla Avenue extension, Sangjani Interchange 43% built

The Capital Development Authority says 43 per cent of the work on the Margalla Avenue extension and Sangjani Interchange is finished. The 2.7-kilometre extension will link N5 to the M1 Motorway.

Margalla Avenue extension, Sangjani Interchange 43% built
Photo: Pexels / Pixabay
KEY POINTS
  • CDA says 43 per cent of the project is complete
  • The extension is about 2.7 km long within Islamabad Capital Territory
  • Underpass structure is done; loops and ramps are in final stages
  • Four of five culverts have been finished
43%Overall completion
about 2.7 kmExtension length
4 of 5Culverts finished

The Capital Development Authority (CDA) said on Monday that overall progress on the Margalla Avenue extension from N5 to the M1 Motorway, together with the Sangjani Interchange, has reached 43 per cent. Construction is continuing around the clock, according to the authority.

The extension runs about 2.7 kilometres within the limits of Islamabad Capital Territory. Work is under way on several sections at once, including the service road that connects to the main carriageway, which is moving ahead steadily.

On the road section, the CDA said the structure of the underpass is finished, including its concrete walls and footing slabs. Earth filling on the left and right sides of the underpass is expected to be completed shortly. The loops and ramps have reached their final stages.

At the Sangjani Interchange, piling is complete and steel fixing is now going on. Minute Mirror reported that girder-related work has also been finished, while remaining excavation is expected to end soon.

Piling and excavation for the abutments on both sides of the N5 bridge are complete. Four of the project's five culverts have been finished, and work on the last one continues.

CDA Chairman Sohail Ashraf has directed departments and construction teams to keep construction standards high and finish the project within the set timeframe. He said the project would ease travel to and from Islamabad and improve access to the airport once complete.

According to the reports, the project will directly connect N5 (G.T. Road) with the M1 Motorway through Sangjani. It is expected to give a faster route towards Islamabad International Airport and to reduce traffic pressure on Srinagar Highway and Kashmir Highway. It will also serve as an alternative entry point for vehicles coming from Khyber Pakhtunkhwa, Punjab and the northern areas.

Why it matters for Pakistan

Commuters travelling between Islamabad and Rawalpindi, and those arriving from Khyber Pakhtunkhwa, Punjab and the northern areas, are the ones whose routes would change. The CDA says the link will offer a faster way towards Islamabad International Airport. It is also expected to reduce traffic on Srinagar Highway and Kashmir Highway, which are used daily by people in the twin cities.