KP plans Rs18.58bn Mansehra water supply scheme to serve till 2040
The Khyber Pakhtunkhwa government plans a gravity-flow drinking water project in Mansehra costing Rs18,583.41 million. APP reported that the Saudi Fund for Development will cover 39.6 per cent of the cost.

- Total cost of the Mansehra project is Rs18,583.41 million
- KP will pay Rs11.23 billion and the Saudi Fund for Development Rs7.35 billion
- Raw water will come from Neeli Nadi through a 64.7-kilometre pipeline
- The scheme is designed for an estimated population of 201,249
The Khyber Pakhtunkhwa government is set to carry out a gravity-flow water supply project in Mansehra to ease the city's growing shortage of drinking water, the Associated Press of Pakistan reported. The scheme is meant to provide a sustainable supply to residents until 2040.
According to documents available with Wealth Pakistan, the project is designed for an estimated population of 201,249. Mansehra's present population is 138,143. The city currently receives 0.58 million imperial gallons per day (MGD), while its projected daily requirement is 5.49 MGD.
Raw water will be carried from Neeli Nadi through a 600-millimetre-diameter mild steel pipeline, 64.7 kilometres long, using gravity flow. A treatment plant with a capacity of 240 litres per second, about 4.6 MGD, will treat the water.
The plan includes 309 kilometres of distribution pipelines and consumer water meters. It also provides for 15 high-ground reservoirs, of which eight are new and seven already exist. Other components are a 23.8-kilometre transmission system for treated water, intake structures, access roads, cross-drainage works and modern monitoring equipment.
The total cost is Rs18,583.41 million. Of this, Rs17,144.09 million, or 92.3 per cent, is for direct construction and development, and Rs1,439.33 million is for indirect expenses. The raw water pipeline is estimated at Rs7.85 billion, and Rs2.76 billion is set aside for geological hazard management and landslide mitigation.
The provincial government and the Saudi Fund for Development (SFD) will finance the project jointly. KP will contribute Rs11.23 billion, or 60.4 per cent, and the SFD will provide Rs7.35 billion, or 39.6 per cent.
The feasibility study and engineering design were prepared in 2011-12, and an initial PC-I worth Rs4.4 billion followed in 2014. The SFD agreed to finance the scheme in January 2019. A revised PC-I was prepared and approved in 2022-23, and administrative approval was granted on April 16, 2024.
Why it matters for Pakistan
Residents of Mansehra face a growing drinking water shortage. The city now receives 0.58 MGD against a projected requirement of 5.49 MGD, according to project documents cited by APP. The scheme is designed to serve an estimated 201,249 people, up from the current population of 138,143. It also includes consumer water meters and 309 kilometres of distribution pipelines.